The Park Lawn Road on-ramp to the westbound Gardiner Expressway is scheduled to reopen at 6 a.m. Friday, November 27, 2026, after bridge replacement work finished two months ahead of schedule, the City of Toronto says.
The city says the reopening will restore access for approximately 15,000 drivers a day, including truck drivers serving the Ontario Food Terminal and businesses across the region.
Crews replaced the single-lane bridge carrying on-ramp traffic over Mimico Creek. The city credits contractor incentives and permission to work around the clock, seven days a week, with reducing the reconstruction period from six months to four. Work began in August 2026.
The Mimico Creek bridge was one of five bridges included in an early works contract for Section 3 of the Gardiner Expressway Strategic Rehabilitation Plan because it required critical repairs, according to the city. That section extends from Highway 427 to the Humber River, with full rehabilitation anticipated to begin in 2028.
The city says the Gardiner has been in service for more than 60 years and is nearing the end of its original design life because of weathering, salt and increasing traffic loads. Council adopted the six-project rehabilitation plan in 2016; its first section was completed in 2021 and its second in 2025.
Under the Ontario-Toronto New Deal, ownership and maintenance of the Gardiner and Don Valley Parkway are set to transfer to the province in fall 2027, the city says. Ontario is providing up to $353 million for operation and maintenance until the transfer is complete.



Leave a comment
Join the discussion. Please follow our Community Standards.
Sign in or create an account to leave a comment.
Choose your public display name before submitting. Your email address stays private.
No published comments yet.