editorial illustration: Hamilton staff propose late 2028 for final recommendations on AI data centres

Hamilton residents could see proposed zoning changes for artificial intelligence data centres in 2028. An interim report on the December 1 Planning Committee agenda sets out a two-year review, with a public meeting and final recommendations planned for the last quarter of 2028. Council can shorten that timetable.

The schedule would extend well beyond the original request. In June, council asked staff to report back on the review and possible action by the second quarter of 2027. Under the new work plan, the first report at that point would cover the background and technical studies. A second report by the end of 2027 would set out findings and what staff heard from residents and Indigenous communities.

The city would then put draft changes to its Official Plan and zoning bylaw before the public, with an open house in the third quarter of 2028. The final report would go to Planning Committee for a statutory public meeting later that year.

Staff want to examine electricity and water demand alongside the permanent jobs, tax revenue and infrastructure costs a facility might bring to Hamilton. They estimate $200,000 for outside expertise, including support for consultation. The Planning Division has included a funding request in its proposed 2027 capital budget.

The December 1 item asks for direction on the study and the consultation plan. Any zoning amendments would come back to the city for a future decision.