EverWind says its planned $10-billion artificial intelligence data centre at Point Tupper, near Port Hawkesbury, N.S., remains on track to open in 2027 after signing power agreements with Nova Scotia Power, even as opponents raise concerns about electricity and water use.
The privately funded project at EverWind’s existing Cape Breton site has secured a long-term lease with AI developer Anthropic, Global News reported. EverWind signed two agreements with the utility last week as it works toward connecting the facility to the provincial grid.
Brendan Chard, EverWind’s vice-president of power, told Global News that the company’s arrangements include covering the additional costs of supplying electricity to the facility, rather than passing them on to other customers.
The electric service contract covers the first, 95-megawatt phase. Power will be supplied on an interruptible basis, allowing the utility to disconnect the centre when the grid is under pressure.
“We’re prepared to cut service with 10 minutes’ notice from the grid operator if required at any point in time,” Chard said.
Batteries or a backup diesel generator would power the facility during those interruptions, he said.
EverWind ultimately intends to supply much of the centre’s power through proposed wind projects. However, the first turbines are not expected to operate until 2028, leaving the facility dependent on Nova Scotia Power’s grid during its first year. Chard said the company is working to secure permits and maintain its 2027 opening target.
Protests have taken place across Nova Scotia since the project was announced a month ago, according to Global News.
Nick Tsergas, a science and technology journalist who founded StopTheDataCentre.ca, raised concerns about AI facilities’ electricity demand and the cooling required to manage the heat they produce. He also argued that assessing water demand requires looking beyond a data centre’s cooling loop to associated power-generating equipment.
EverWind says its Point Tupper design uses a sealed water–glycol cooling loop. Heat would be removed mainly through air cooling, with water-assisted cooling during the hottest weather. The company says Nova Scotia’s cooler climate would reduce cooling-water requirements for much of the year.
EverWind will initially pay an interim large industrial tariff. Nova Scotia Power said a new rate is needed because existing tariffs were not designed for a customer of this scale, and said existing customers should not bear the costs of new developments.
A second phase could expand the project to 420 megawatts in 2028, subject to approvals and conditions.




Leave a comment
Join the discussion. Please follow our Community Standards.
Sign in or create an account to leave a comment.
Choose your public display name before submitting. Your email address stays private.
No published comments yet.