Agratas faces another contractor change at its £5.2-billion electric-vehicle battery factory in Bridgwater, Somerset, raising fresh questions about the timetable for a project intended to supply Jaguar Land Rover and strengthen Britain’s automotive industry.
TSL has decided to leave after failing to agree terms with Agratas, according to reporting by The Guardian’s Jasper Jolly, citing three sources. It would be the second main building contractor to depart in five months.
Two sources told the newspaper that disagreements over the project’s cost and timeline prevented an agreement. TSL, formally known as Tonroe Group, is expected to leave the site within two or three months, the report said.
No replacement main contractor is lined up, according to The Guardian. NG Bailey, which handles mechanical, electrical and plumbing work on the project, was identified as a possible option to take over the overall build, rather than a confirmed successor.
Agratas and Jaguar Land Rover are both owned by India’s Tata Group. The British government has pledged £380 million in support for the factory, although not all of that funding has been paid.
When Tata announced the project in 2023, production was expected to begin in 2026, with employment potentially reaching 4,200. The start was subsequently moved to 2027. The latest target is January 2028, and Agratas has not announced another postponement.
“We are on track to meet our customer requirements,” an Agratas spokesperson told The Guardian.
“The Somerset site is a large and complex industrialisation project, and all of our supplier partners are supporting us well as we prepare for the facility’s launch phase.”
The contractor uncertainty follows Agratas’s dismissal of Sir Robert McAlpine in June. Despite those difficulties, the building’s shell is mostly complete, and National Grid has begun work on the electricity substation needed to power battery production.
The Guardian reported that Jaguar Land Rover has secured batteries from other suppliers, meaning its plans to increase electric Land Rover and Jaguar sales are not expected to be affected. Those initial vehicles, however, will not use British-made batteries.
TSL and Jaguar Land Rover declined to comment to the newspaper. NG Bailey was approached for comment.
Source: The Guardian’s reporting on the Agratas factory contractor change.



Leave a comment
Join the discussion. Please follow our Community Standards.
Sign in or create an account to leave a comment.
Choose your public display name before submitting. Your email address stays private.
No published comments yet.